Project Engineers for commercial retail strip center with pre-cast concrete detention under parking lot along Route 25, Carpentersville (project photos on our website at landtechnologyinc.com under “Projects”).  This project contained all of the services listed below plus underground detention and testimony before the Village Plan Commission and Village Board in support of underground storage.

            Work included:

  • Boundary Survey
  • Topographic Study
  • Site Engineering
  • Grading Plan
  • Storm Water Management Plans
    • Calculations and design of detention basin
  • Construction Staking of all improvements
  • Building
  • Parking Lot
  • Sewers
    • As-Built Drawings of completed project
    • Surveys (Plat of Consolidation, Spot, Final Survey)